Converting BOQ to SOV Import Template

Last Updated: September 6, 2024


Schedule of Values



A Schedule of Values (SOV) is a crucial document used to allocate and track the value of various work components or items within a contract. It helps to keep track of progress and ensure accurate billing throughout the project. In this article, we will guide you to set up your Schedule of Values



Converting BOQ to SOV Import Template


Step 1: Setting up template


  1. Access your Project Dashboard to start the process


  1. Within your project, click on Modules


Fig.1: Dashboard



  1. Click on Accomplishment Report


Fig.2: Accomplishment Report



  1. In the Accomplishment Report section, click on Download Template. The download will start shortly after.


Fig.3: Download Template



Step 2: Inputting Values to the Template



  1. Open the downloaded template and click on Enable Editing to make changes



Fig.4: Template



  1. Input the necessary information. Refer to figure 5 for transferring values from BOQ to SOV template.
    Optional Value: Contract Package Optional Information:



Fig.5: BOQ and SOV



  1. Item Number must be a unique identifier and should always have a value.


  1. Calculating Values. If any of the three essential components (Total Cost, Planned Quantity, or Unit Price) are not specified on your BOQ, you can use the following formulas to calculate the missing value:


  • Total Cost = Planned Quantity x Unit Price
  • Planned Quantity = Total Cost / Unit Price
  • Unit Price = Total Cost / Planned Quantity
  • Planned Percent Weight = Line Item Total Cost / Project Cost


Ensure all Planned Percent Weight value sum up to 1 or 100%



Step 2.1: Detail Explanation of BOQ to SOV transformation



  1. Item Categories: These are broad classifications that group similar items together. 


  1. Item Numbers: These are unique identifiers assigned to each individual item within a category. They should be sequential and comprehensive to ensure accurate tracking and reporting.


Fig.6: with Item Categories but Incomplete Unique Identifier


Fig.7: with Complete Unique Identifier and Categories



  1. Item Relationship or Hierarchy. When an item in the Bill of Quantities (BOQ) serves as a parent to other items, clearly indicate this hierarchical relationship in the Description field. For example, if 'Floor Preparations' is a parent category to 'Civil Works,' specify this in the Description field.


Fig.8: (left) incomplete item description. (right) complete item description



Step 3: Saving template



  1. Once you have entered all the required data, save the SOV template


  1. Return to the Accomplishment Report section and click on Import File to upload your SOV template.


Fig.8: Import



  1. Click on OK to finish the set up.


Fig.9: Pop up





Managing Accomplishment Report Module
Viewing the Accomplished Tasks
Reviewing and Approving Accomplishment Reports
Navigating Accomplishment Report via Steer Mobile app
Submitting an Accomplishment Report
SOV Setup